Scholar Garage Addition

Scholar Garage Addition PROJECT DETAILS Type: Addition – Second Story (Office) Location: Nexton Year Completed: 2023 Timeframe: _____ __ Month HOA Approval Process 2 Week County Permit Process 4 1/2 Month Build Time Added Sq. Ft: 1,069 Our clients needed to move their home office to make room for their growing family so we added a […]

Pine Bark Garage Addition

Pine Bark Garage Addition PROJECT DETAILS Type: Addition Location: Nexton Sq. Ft: 500 Year Completed: 2023 This project involved expanding an existing two-car garage with a second-story addition to provide additional living space.  We began by carefully removing the existing roof while preserving the trusses to maintain structural stability. To comply with local HOA height […]